VICTORIA PARK TUNNEL - ENGINEERING
|
Road Standards and Design Features
- Improved standard of median and edge barriers.
- Ability to dynamically manage the motorway considering traffic and bus priority requirements.
- Better connections with the central motorway improvements.
- Make best use of the unused traffic capacity of the Auckland Harbour
Bridge by increasing the capacity of its approaches.
Geotechnical
- Most of this section of the motorway is built on reclaimed land.
- Geotechnical testing has taken place to consider groundwater
flows and soil contamination.
Existing Services
- The Tunnel impacts on sewerage and stormwater pipelines and
telecommunications cables.
- These services will be relocated as part of the project.
Constructability
- The Tunnel will be constructed while minimising disruption to
traffic.
Proposed
|
|
|
|
|
|
|